Please enjoy this presentation of a kitchen remodel from tearout to finish.  The kitchen  remodel sequence shown here took 3 weeks from start to finish.  Thank you to the Hoyer family for providing these great pictures!  To view as a slide show, click on any picture to open it, then click the Start button.

Providing a full range of remodeling services including: custom cabinets,  cabinet refacing,  granite and stone, tile, custom countertop overlay, windows, doors, painting, electrical,  plumbing, crown and finish moulding, drywall, flooring and concrete overlay, and much, much more!

tn_1.__Dumpster_delivered_on_site.jpg
1. Dumpster placed on site
tn_2._B4_Dining_Room_Angle_1.jpg
2. B4 Angle 1
tn_3._B4_Angle_2.jpg
3. B4 Angle 2
tn_4._Day_1_Tearout.jpg
4. Day 1 tearout
tn_5._Tearout_2.jpg
5. Tearout 2
tn_6._Tearout_3.jpg
6. Tearout 3
tn_7._End_of_Day_1.jpg
7. End of Day 1
tn_8._Rebuild_started.jpg
8. Rebuild started
tn_9._New_wall_built.jpg
9. New Wall Built
tn_a._Utility_rough-in_started.jpg
10. Utility rough in laid out
tn_b_Plumbing_and_Electrical_installed.jpg
11. Plumbing and Electrical roughed in
tn_c Electrical and phone installed.jpg
12. Electrical and phone installed
tn_d13._End_of_week_1_angle_1.jpg
13. End of Week 1 Angle 1
tn_e.jpg
14. Angle 2 windows & utilities in
tn_f.jpg
15 Week 2 Drywall installed
tn_g.jpg
16. Angle 2 drywall installed
tn_h.jpg
17. Tape & Mud started
tn_i.jpg
18. Texture and paint finished
tn_j.jpg
19. Cabinets delivered
tn_k.jpg
20. Cabinet install begun
tn_l.jpg
21. Cabinet install begun 2
tn_m.jpg
22. lower cabinets installed
tn_n.jpg
23. lower cabinets installed 2
tn_o.jpg
24. upper cabinet w/crown installed
tn_p.jpg
25. rough top with appliance cutouts
tn_q.jpg
26. Custom tile counertop begun
tn_r.jpg
27. Custom tile install
tn_s.jpg
28. Countertop complete, appliances in
tn_t.jpg
29 Kitchen complete w/o flooring
tn_u.jpg
30. Cork flooring installed
tn_v.JPG
Total time to completion - 3 weeks